Floor Screeding of 2500 sq.m completed in 4.5 days
March 2012
Summary of project
- Project programme was 1 week to include weekend working if necessary, completed in 4.5 days.
- Floor Area = 2500sm x 75mm nominal depth.
![floo-rarea2500smx75mm-nominal-depth](https://www.cscscreeding.co.uk/hs-fs/hubfs/floo-rarea2500smx75mm-nominal-depth.webp?width=580&height=435&name=floo-rarea2500smx75mm-nominal-depth.webp)
- The screed specification used FlexiDry F3 at a nominal depth of 75mm to encapsulate and conduct the heat from the underfloor heating system.
- Quantity of Sand = 340 tonnes
![quantity-of-sand40tonnes](https://www.cscscreeding.co.uk/hs-fs/hubfs/quantity-of-sand40tonnes.webp?width=580&height=435&name=quantity-of-sand40tonnes.webp)
- Sand was delivered via 8 wheeler tipper truck with 20 tonnes and in some cases, 30 tonnes on an articulated tipper. Circa 16 lorry loads.
- Pumping distance was around 90m.
- 4 screed pumps in use on the 1st day and 3 screed pumps for the remaining 3.5 days.
![Sand-and-pump](https://www.cscscreeding.co.uk/hs-fs/hubfs/Sand-and-pump.webp?width=580&height=435&name=Sand-and-pump.webp)
- 4th machine on site as a backup in case of any form of mechanical breakdown.
- 4 screeders and 6 general pump operatives on the 1st day and then dropped off to 3 screeders and 4 general operatives for the remainder.
- End client was Keuhne & Nagel, principal contractor was Readie Construction Ltd and our client was TMCD Developments Ltd.