Parkfield School Hendon

May 2009

Parkfield School Hendon, is one of the latest projects to use the innovative FlexiDry fast drying additive. This covered an area of 3020sm using the FlexiDry F3 21 day drying accelerator in order to speed up the application of final floor finishes. The screed was installed in 14 days and did not require a polythene curing protection as per standard screed systems. Willmot Dixon signed off the project at first request and feedback was very positive. CSC expect to secure further tenders, based on this proven ability to support demanding project timelines.