| Mapei High Performance Screeds |
| Mapei Mapefluid PZ500 |
Fast drying additive |
3mm per day up to 75mm |
24 hours |
PZ500 DataSheet.pdf |
| Mapei Topcem |
Fast drying cement replacement |
Dry in 7 days regardless of thickness. |
12 hours |
topcem.pdf |
Mapei Mapecem |
Ultra fast drying cement replacement |
Can be tiled within 3 hours completely dry in 24 hours |
2-3 hours |
mapecem.pdf |
| Mapei Ultraplan |
Fast drying cementitious self levelling screed, up to 10mm thickness |
12 hours before subsequent bonding. |
3 hours |
ultraplan.pdf |
| Mapei Ultraplan Maxi |
Fast drying cementitious self levelling screed, up to 10mm thickness |
2 days to 2-3 weeks depending on thickness |
3 hours |
ultraplanmaxi.pdf |
| Mapei Latex Plan |
2-part cement based smoothing and levelling compound, up to 10mm |
12 hours before laying floorcovering |
1.5-2 hours |
latexplan.pdf |
| Mapei Planicrete |
SBR Bonding Agent |
N/A |
N/A |
planicrete.pdf |
| Traditional site mix |
| Traditional Fibrescreed |
1:4 cement sand screed with polypropylene fibres |
1mm per day up to 40mm, then .5mm per day |
24-48 hours |
N/A |
| Traditional Fibrescreed |
1:3 cement sand screed with polypropylene fibres |
1.2mm per day up 40mm, then .5mm per day |
24 hours |
N/A |
| Calcium Sulphate screeds |
| Anhydrite Lafarge Gyvlon |
Self levelling calcium sulphate screed |
1mm per day up to 40mm |
24-48 hours |
gyvlon.pdf |
| Hemihydrite Cemex Supaflo |
Self levelling calcium sulphate screed |
1mm per day |
24-48 hours |
Supaflo.pdf |